Welcome
The facilitators opened the meeting at 6:05 pm and reviewed the agenda to set the expectations
for the meeting. Participants introduced themselves by stating their name, affiliation, and place
of residence. The facilitators sent a sign-in sheet around the room.
The facilitators stated that the next two BAG meetings, as selected by the BAG members, would
be held August 9th in Wright and October 11th in Hulett. The Wright meeting will also include a
coal mine tour earlier in the afternoon. The BAG then scheduled the next subsequent meeting
for December 13th in Moorcroft. The BAG elected to change the meeting time for the December
meeting from the evening to the afternoon (1:00 pm to 4:00 pm).
Updates on Other Basin Plans
Jon Wade updated the BAG on the status of the plans for the other basins. The Powder/Tongue
Basin planning process is on a similar time frame to that of the Northeast River Basins. He
reported the plan for the Green River Basin has been completed and the task of placing the plan
on the website is nearly complete. The review of the draft plan for the Bear River Basin has
been completed and the plan is being finalized by the consultants. Consultants have been
selected for the two new studies, the Wind/Bighorn Basins and the Snake/Salt Basins. BAG
formation for these two new studies began in May and will be completed in June.
Jon reminded the BAG of the coal mine tour to be held prior to the August BAG meeting. Tom
Doll of Barrett Resources offered a tour of CBM activities that could be held in conjunction with
the coal mine tour. State staff will try and arrange such a combination tour and will notify BAG
members in advance.
Jon then introduced Pat Tyrrell who made a few remarks regarding his first few months as the
new Wyoming State Engineer.
Conclusion of the Issues Identification Process
The facilitators explained that at previous meetings, BAG members combined, rearranged, and
prioritized water resource sub-issues under main categories. This process continued with the last
and final issue, which was that of Regulatory as presented in the following table.
Issue: Regulatory Subissues: | Upper Belle Fourche |
Lower Belle Fourche | Niobrara River | Little Missouri |
Cheyenne River |
EPA: Wetlands, AFO/CAFO, TMDL's | 1 | 1 |
1 | 1 | 1 |
BLM: T&E Species | 1 | 1 |
1 | 1 | 1 |
DEQ/WQD: stream classification, source point pollution problems |
1 | 1 |
1 | 1 | 1 |
SEO: groundwater permitting process | 1 | 1 |
2 | 1 | 1 |
USFWS: T&E Species | 1 | 1 |
1 | 1 | 1 |
Corps of Engineers: wetlands | 1 | 1 |
1 | 1 | 1 |
Conflicting government goals with private owners caught in the middle |
1 | 1 |
1 | 1 | 1 |
US Bureau of Reclamation | 1 | 1 |
X | X | X |
Game & Fish | 1 | 1 |
1 | 1 | 1 |
Forest Management, or lack thereof, affecting water quality | 1 |
1 | X | 1 | 1 |
Governmental taking of water and/or land | 1 | 1 |
1 | 1 | 1 |
Consultant Update - HKM Engineering
Wade Irion reported that the preliminary results of Task 2 were presented to the BAG at the last
meeting and this task has been completed except for a couple remaining items. Collection of
data on future recreational and industrial water use is in process at this time. Gary Watts, the
economist for the team, is conducting this later investigation.
The majority of the effort exerted by the consultants at this time has been on Task 3, the
determination of available surface water and groundwater. Wade then explained this task
consists of the following:
- Surface water data collection and study period selection;
- Surface water data synthesis;
- Spreadsheet model development;
- Surface water model calibration;
- Available surface water determination; and,
- Available groundwater determination (based on previous and ongoing groundwater
evaluations).
Surface Water Hydrology - HKM Engineering
Wade Irion then explained the surface water hydrology work required to develop the spreadsheet
models. These models are then used to determine the availability of surface water. The
presentation specifically addressed how existing water data was collected, how the study period
of 1970 to 1999 was selected, and how missing data was synthesized.
Question: Was the streamflow data below Keyhole Reservoir adjusted for the operation of the
reservoir before selecting wet, normal, and dry years?
Response: The selection of wet, normal, and dry years was not based on records of flow below
Keyhole because these flows are severely affected by the operation of the reservoir.
Question: Was National Weather Service data used to synthesize streamflow data?
Response: No. Concurrent monthly streamflows from nearby hydrologically similar gaged
streams were used in lieu of precipitation data to estimate missing monthly streamflows.
Stock Reservoir Identification Discussion - Chace Tavelli, SEO
In response to a BAG request to quantify evaporation from stock reservoirs, Chace reported that
the planning team is evaluating the best method to determine the number of stock reservoirs in
the sub-basins. It appears that only a portion of the reservoirs are permitted making it difficult to
determine the actual number of stock reservoirs. He reported on a recent analysis he made of the
SEO water right database that revealed approximately 1,900 permitted stock reservoirs in the
Belle Fourche drainage. He explained that the latest priority water right in the database was June
30, 2000, and that the surface water database is updated on a frequency of approximately every
3-4 months.
To estimate the percentage of reservoirs that are permitted versus those not permitted, HKM
Engineering plotted the permitted reservoirs on sample digital quads from various areas in the
drainage. Chace then distributed HKM's prints of the digital quads and noted there appeared to
be a large percentage of stock reservoirs that were not permitted.
Question: Does the permitting process identify the source of the water?
SEO Response: Yes, the source of the water is noted on the permit, however, if the pond
receives CBM water it is not always noted on the permit for older permits. The newer permits,
dating back to approximately February 2001, started specifying CBM discharge water as a
source of supply.
Question: Does the permitting process consider the downstream water quality impacts of the
discharge?
DEQ Response: The SEO permitting process does not consider downstream water quality
impacts. The NPDES permitting process of DEQ addresses downstream water quality impacts
of discharge. Water quality parameters of discharge water are measured at the point of
discharge.
Question: How will the number of nonpermitted reservoirs be determined?
SEO Response: Several methods are being evaluated to come up with this estimate.
Chace emphasized that it was very important to come up with an acceptable estimate of the
number of stock reservoirs in the Northeast river basins. The BAG has been very adamant that
an acceptable number be developed. Both the State and HKM are trying to determine a
reasonable process to quantify the number of stock reservoirs and insure that the estimate is a
number the BAG is comfortable with, and is representative of the situation.
Total Maximum Daily Loads (TMDL) - Jim Eisenhauer, DEQ
Jim gave an overview of Total Maximum Daily Load (TMDL) regulations. His presentation
described water body classification and the determination of designated uses for the four classes
of water. He explained how if water bodies were not supporting their designated uses, they must
be listed on the states' 303(d) list as impaired. Each listed water body must be given a priority
(low, medium, or high). Jim then described the process that must be implemented to return the
stream to its designated use and remove it from the impaired list. Wyoming is one of the few
states that allow a local group to develop a watershed plan in lieu of establishing a TMDL. In
this case, DEQ will reprioritize the development of a TMDL to "low" for this water body, but it
is not removed from the 303(d) list of impaired waters. DEQ then steps back and allows the
local stakeholders to address the water quality issues associated with the water body. If progress
is not shown, or interest wanes, DEQ will then re-prioritize to original status and begin
development of the TMDL.
The meeting was adjourned at approximately 9:00 pm.
|